Building permit — Addition / Alteration · BP-2020-03110
Field Review - Addition / Alteration - Interior alterations to provide improvements to Cathlab 3 on the ground floor of this Vancouver General Hospital (Jim Pattison Pavillion South building) on this site. OK for Field Review per W.Wong, October 5, 2020 CRP Schedule A & Architectural Schedule B submitted by Patrick Yue, 778.688.7317 Structural Schedule B submitted by Brett Halicki, P.Eng., 604.688.9861 Mechanical & Plumbing Schedule B submitted by Mark Yeung, P.Eng., 604.559.8809 Electrical Schedule B submitted by Gary Yeung, P.Eng., 604.662.3555 Note: Energy trigger chosen; E2 - Lighting - Upgrade to Local Control (per 9.4.1.1.(a) of ASHRAE 90.1-2016
Source: Vancouver — Issued permits — 2020-2022. Contains information licensed under the Open Government Licence – Vancouver.