Building permit — Addition / Alteration · BP-2022-03885
Field Review - Addition / Alteration - Exterior and interior alterations to renovate the existing one family dwelling. The scope includes to install the interconnecting stairs between main floor and basement Scope of Work: Remove and fill a front door on west elevation, install new interior stairs and revise surrounding walls, decommission two electric cookers, remove and replace doors and windows on east elevation, upgrade existing kitchen, and relocate interior walls Revision #1 Basement fl - Updated both existing & proposed plans to show drop beam - Relocate door to bathroom & removed interior walls of existing closet to make the washroom bigger - Removed interior walls to create larger storage room on the North side - Layout changes to furnace room, demolished & install interior walls and install new sliding door - Removed 3 interior doors & infilled interior walls to match existing - Increase construction cost of 5,000.00 Sch B (Struct): Carlos Chiu, P.Eng #19417, 604-737-9830, Chiu Hippmann Engineering Inc. REUP upgrades: (Required 2pts; Proposed 2 pts) 1. Attic Insulation: If < R12 increase to R28, if > R12 increase to R40 (nomianl values) (1pt) 2. Ventilation and Controls: All bathrooms require exhaust fans on timers or humidistats & install smart home thermostat (1pt)
Source: Vancouver — Issued permits — 2020-2022. Contains information licensed under the Open Government Licence – Vancouver.
Comments
New comments are public while this project is public. Earlier members-only comments remain restricted.
Sign in to comment.
No comments on this page.